FG Targets December Completion of Eko Bridge Repairs, Full Traffic Restoration

By Atlantic Reports
The Minister of Works, Sen. Dave Umahi, gave the assurance on Monday, November 23, during an inspection of the bridge, which suffered structural damage linked to illegal sand mining activities.
Umahi disclosed that the underwater section was damaged by an illegal sand miner, whose dredging equipment subsequently sank at the site.
He explained that the damage affected part of the bridge's structural foundation, prompting the closure of half of the carriageway to protect motorists and allow emergency repair work to proceed.
According to the minister, the decision to maintain traffic on the remaining half of the carriageway was intended to minimise disruption for commuters using the busy transport corridor.
Government Monitors Structural Safety
Umahi said the Federal Government was monitoring cracks associated with the damage to the bridge's pile cap, expressing relief that they had not shown signs of further development.
He explained that engineers had put mechanisms in place to monitor the condition of the affected structure.
The minister noted that the entire carriageway would have been closed if the cracks had continued to develop, potentially causing greater inconvenience to motorists.
Four Deep Piles to Reinforce Bridge
The Federal Government engaged Buildwell Construction Company to undertake emergency restoration work, including the removal of the submerged dredger.
Umahi said the technical restoration involved driving four piles to a depth of 54 metres above water level.
The piles would be connected through a newly constructed pile cap, followed by the installation of a structural frame and other supporting elements to reconnect the structure to the bridge's floor slab.
He commended Buildwell for its pace of work, saying the contractor had promised to complete the assignment by December.
The minister also disclosed that the government had made a part payment to the contractor and would engage the Minister of Finance to facilitate the release of the outstanding funds.
He said the illegal sand miner responsible for the damage would be taken to court and made to pay for the destruction.
Other Sections Also Receiving Attention
Umahi expressed satisfaction with the supervision of the project, particularly the work of the resident engineer, Mrs Fisayo Badmos.
He added that the Federal Government was intervening in other sections of Eko Bridge as part of efforts to address infrastructure concerns.
The December completion target is expected to bring relief to commuters who have had to contend with restricted traffic movement since the damaged section was closed.
However, the full restoration of traffic will depend on the timely completion of the repairs, the release of outstanding project funds and confirmation that the bridge's structural integrity has been restored.
The government has yet to provide further details on the total cost of the emergency intervention or the specific legal process for recovering the repair expenses from the alleged illegal miner.
Atlantic Reports: Voices. People. Facts.
Written by
Atlantic Reports Admin
Comments
- Be the first to comment.