FG Targets March 2027 Inauguration of Abeokuta Transmission Substation

By Atlantic Reports Admin· 27 November 2026
 FG Targets March 2027 Inauguration of Abeokuta Transmission Substation
Share:

 

By Atlantic Reports

The Minister of Power, Mr Joseph Tegbe, disclosed this on Friday in Abeokuta after inspecting the ongoing project, expressing satisfaction with the progress of work.

Tegbe said the project had reached an advanced stage, with most of the equipment already installed, while some remaining components were awaiting installation and testing.

According to him, the facility is expected to undergo cold commissioning in December 2026, followed by hot commissioning and energisation ahead of its planned inauguration in March 2027.

Five substations under transmission expansion programme

The minister explained that the Abeokuta project is one of five substations being developed under the first batch of the Federal Government's transmission expansion programme.

The other locations are Ayede in Oyo State, Sokoto, Offa in Kwara State and Onitsha in Anambra State.

He said the five projects would collectively add 986 megawatts to Nigeria's transmission capacity.

Tegbe stressed that expanding electricity generation without corresponding investments in transmission and distribution infrastructure would continue to limit the country's ability to deliver reliable power to consumers.

He added that the government was adopting a coordinated approach to address challenges across the electricity value chain.

Government engages electricity distribution companies

The minister disclosed plans to meet with four electricity distribution companies, namely Abuja, Ikeja, Eko and Ibadan, to discuss challenges affecting electricity delivery.

He said the government was working with gas suppliers, generating companies, the Nigerian National Petroleum Company Limited and relevant ministries to tackle bottlenecks affecting the sector.

The approach, he explained, was intended to address problems from gas supply and electricity generation to transmission, distribution and delivery to consumers.

Nigeria targets 10,000MW generation by 2031

Speaking on the Federal Government's ambition to build a $1 trillion economy, Tegbe described reliable electricity as essential to industrialisation, economic growth and national development.

He said Nigeria was targeting 10,000 megawatts of electricity generation by 2031, alongside transmission capacity of at least 19,000 megawatts.

According to him, achieving these targets would improve electricity supply to commercial and industrial users while supporting the country's broader economic ambitions.

Abeokuta project to add 480MW to Ogun industrial corridor

Also speaking, the Managing Director of FGN Power Company, Mr Kenny Anuwe, said the upgraded Abeokuta substation would inject an additional 480 megawatts into Ogun State's industrial corridor.

Anuwe explained that the project, under the first batch of Phase One of the Presidential Power Initiative (PPI), would transform the existing 132/33kV facility into a modern 330/132/33kV substation within an 18-month implementation period.

He said the upgraded facility was expected to improve electricity evacuation, strengthen network reliability and accommodate rising demand from industries, businesses and residential consumers.

According to him, the Presidential Power Initiative represents a Federal Government intervention aimed at addressing longstanding infrastructure constraints across Nigeria's electricity generation, transmission and distribution networks.

Siemens partnership and previous achievements

Anuwe said the initiative had recorded progress through its partnership with Siemens Energy.

He disclosed that the pilot phase delivered 10 power transformers and 10 mobile substations, adding approximately 1,080 megawatts of electricity wheeling capacity nationwide.

He reaffirmed FGN Power Company's commitment to coordinating stakeholders and ensuring that the initiative translated into measurable improvements in electricity delivery.

Infrastructure expansion and the delivery question

While the planned substation upgrade represents an important addition to Ogun State's electricity infrastructure, its actual impact will depend on successful commissioning, effective integration into the national grid and the capacity of distribution networks to deliver the additional power to consumers.

The Federal Government's broader targets will also require sustained investment, reliable gas supply, adequate generation and improvements in distribution infrastructure.

For businesses and households in Ogun State, the critical measure will ultimately be whether the investment translates into more reliable electricity, fewer supply disruptions and improved conditions for economic activity.